Step 1

Foilboard® GREEN rigid insulation panel should be installed to the underside of the roof purlins to create an airspace.

Step 2

Use full sheets in the areas that they fit. Then measure and cut the smaller areas.

Step 3

Mark the measurements out on the Foilboard® GREEN rigid insulation panel, using the gridlines as a guide. Using a straight edge and a sharp blade/knife, cut the rigid panel to size.

Step 4

Fasten the insulation panel to the purlins with the Foilboard® timber or steel fasteners using 3 per purlin, use either a hammer or drill as required.

Step 5

Tape all penetrations, joints and gaps using Foilboard® Green tape to minimise hot/cold air transfer.

Handling and Storage

Instructions are a guideline only and should be interpreted with consideration for the specific building application. Alternative installation methods may be used provided the airspaces adjacent to the Foilboard® are maintained and the material is non load bearing. All Penetrations must be effectively sealed to reduce any risk of damage caused by possible exposure to extreme radiant heat. Please contact Foilboard Australia Pty Ltd for further information. Safe installation practices are encouraged at all times.

It is recommend that if the product is being stored for extended periods it should be kept clean and dry. Any moisture present between sheets should be dried to prevent potential oxidization and must not be stored with either foil surface in contact with any alkaline materials.

Required to install

Use Foilboard® Standard Fasteners (timber frame) for Foilboard® GREEN 10 & GREEN 15 OR

Use Foilboard®  Ultra Fasteners for Foilboard® GREEN 20 & GREEN 25

(Use Timber or Steel fasteners depending on application)

Foilboard® Green joining or Silver Tape

Foilboard ® Tips

  • The Foilboard® can be installed silver or green side down. The anti-glare green will still reflect heat away.
  • The airspace created by the install will contribute to the thermal resistance of the system.

In need of further technical advice or assistance?

Foilboard® Technical Department is available to assist


Designing a Building?

Designing a Building?

Doing it yourself?

Doing it yourself?

Loader