Foilboard® GREEN rigid insulation panel should be installed to the concrete tilt panel after installing the furring channel clips to the wall.
Mark the measurements out on the Foilboard® GREEN rigid insulation panel, using the gridlines (registered design) as a guide. Using a straight edge and a sharp blade / knife, cut the rigid panel to size.
Position the insulation panel and gently push into position. Then mark all the clips on the back of the Foilboard®.
Using a sharp knife cut a slot where the sheet has been marked to allow the sheet to be pushed into position. Install furring channels to lock into place.
Tape all the penetrating, joints and gaps using Foilboard® GREEN tape, to minimise hot/cold air transfer. Use spacer blocks to improve thermal performance (finest).
Foilboard® Green joining tape
Foilboard® space blocks (optional)